Project background:

Gorilla has developed significant experience in the design and installation of temporary bridges and towers at live events and festivals, a number of bridges and structures were designed and installed Shambala 2019

Gorilla role summary:

The design, install & removal of 2 bridges, 7 security towers and 5 site structures, including marquee facades and DJ towers.

Gorilla role detail:

  • Installation of x2 bridges (1 pedestrian / 1 buggy)
  • 4 man team, 1 telehandler.
  • CAD drawings / Engineering

Event Work:

Gorilla worked with the site team and organiser to facilitate an efficient build up and de-rig.

Timescales involved:

  • 3 day install
  • 1 day de-rig

This was Gorilla’s 1st year working with Standon Calling

Result / Outcome:

The client was delighted with the work undertaken, the process ran more smoothly than it had in previous years.

Client Feedback:

“We needed a number of temporary structures to be designed and built around the festival site, primarily two bridges – one for foot traffic and the other capable fo carrying buggies – seven security towers, and other structures including marquee facades and Dj towers. The team from Gorilla worked with us throughout the process to design, install and de-rig them quickly and efficiently, and we were delighted with the result.”

Graham MacVoy, GMC Events